Master Plan
On June 23, 2022, the SCUSD Board of Trustees approved the Peterson and Patrick Henry Facility Master Plan, the new Laurelwood Master Plan, and Program of Spaces. The design of the new Laurelwood Elementary School began in July 2022. Visit the Bond Department's New Laurelwood Elementary School webpage for construction updates.
Voter-approved general obligation bond Measure BB allocated bond funds to design and build a new elementary school for Laurelwood Elementary on the Patrick Henry Campus and new fields at Peterson Middle School. In order to create a plan that encompasses all of the district's assets, SCUSD has created a master plan for the new Laurelwood Elementary campus and a portion of Peterson Middle School.
Currently, funding is only identified for the new Laurelwood Elementary School and the Peterson track and field. The other improvements identified in the master plan will be completed as funding is secured.
A master plan is a dynamic long-term planning document that provides a visionary site plan to guide future expansion with enhanced student and community access to the sites.
Master Plan Meetings
Upcoming Meetings
We have concluded all Master Plan meetings with Peterson Middle and Laurelwood Elementary Schools.
Past Meetings
March 23, 2023 | Regular Board Meeting | Certification of the CEQA EIR
July 19, 2022 | CEQA Notice of Preparation (NOP) Scoping Meeting
June 23, 2022 | Regular Board Meeting | Presentation to the Board and Final Approval of the Peterson and Patrick Henry Facility Master Plan
- Board Meeting Presentation 6/23/22
- Peterson Laurelwood Facilities Master Plan Booklet
- New Laurelwood Elementary Program
- Meeting Video
June 14, 2022 | Community Meeting #3 | Final Review of the Peterson and Patrick Henry Facility Master Plan | Virtual
May 3, 2022 | Special Board Meeting | Laurelwood Student Capacity
March 24, 2022 | Board Meeting | Laurelwood Student Capacity
February 24, 2022 | Board Meeting | Master Plan Update #2
February 16, 2022 | Master Plan Review with Peterson and Laurelwood SSCs
January 27, 2022 | Master Plan Review with Peterson and Laurelwood Site Administration
January 19, 2022 | Community Meeting #2 | Virtual
December 9, 2021 | Board Meeting | Master Plan Update #1
December 7, 2021 | Meeting with Peterson SSC
December 2, 2021 | Community Meeting #1 | Virtual
December 1, 2021 | Community Meeting #1 | In-Person
November 19, 2021 | Meeting with Laurelwood PTA and SSC Parent Representatives
November 15, 2021 | Meeting with Laurelwood Staff
November 12, 2021 | Meeting with Peterson Staff
November 9, 2021 | Meeting with Peterson and Laurelwood Community Members
November 9, 2021 | Meeting with Peterson Site Administration
August 2, 2021 | Meeting with Laurelwood Site Administration
California Environmental Quality Act (CEQA)
Certification of the CEQA EIR was completed at the March 23, 2023 Board Meeting
The public comment period was November 23 - January 9, 2023.
Questions
If you have questions or would like to be added to the listserv for this project, please email us at PetersonLaurelwoodPlan@scusd.net.